An SPV owned by Greentop Energy Systems S.A., founded in Athens, on 25/11/2011.
Its sole purpose is to develop, construct and operate a cluster of wind and solar energy projects in North Greece, with a total capacity of 161.9MW.
Projects
Project Description
The SPV is developing an 84.6 MW wind project at Perasma – Bougioukli – Daoutli, in the Municipality of Paionia, Regional Unit of Kilkis, Northern Greece, near the border with North Macedonia and within accessible distance from the Port of Thessaloniki.
The wind farm comprises 15 wind turbines with a total installed capacity of 84.6 MW. The project has obtained the relevant production and environmental approvals, including the updated environmental permitting documentation of 2025. A Grid Connection Agreement has also been signed with the Independent Power Transmission Operator (IPTO).
The project is located in a predominantly hilly area with low vegetation. Wind resource assessments have been carried out using meteorological masts and LiDAR measurements to evaluate the site’s wind potential.
The project will be connected to the transmission system through the Pontoiirakleia Substation and the associated 150 kV transmission line, in accordance with the signed Grid Connection Agreement.
Project Description
The SPV is developing two wind projects with a combined installed capacity of 16.5 MW at Kokkini Koryfi – Pyramis, in the Municipality of Paionia, Regional Unit of Kilkis, Northern Greece, adjacent to the 84.6 MW wind project.
The development comprises Pyramis 1 (11 MW) and Pyramis 2 (5.5 MW), with a total of three wind turbines. The projects have obtained the relevant production and environmental approvals, including the updated environmental permitting documentation.
In 2026, a Grid Connection Agreement was signed with the Independent Power Transmission Operator (IPTO).
The projects are planned to connect through the Pontoiirakleia Substation (33/150 kV), utilising the associated transmission infrastructure developed for the GREENTOP EIRINIKO wind energy portfolio.
Project Description
The SPV has developed a 17.7744 MWp solar photovoltaic project at Perasma – Bougioukli – Daoutli, in the Municipality of Paionia, Regional Unit of Kilkis, Northern Greece.
The project has obtained the relevant production and environmental approvals, as well as an Installation Permit.
The photovoltaic plant is in commercial operation.
Project Description
The SPV develops a cluster of twentytwo (22) solar projects on private land with a capacity of 1MW, each in the Prefecture of Kilkis, Municipality of Paionia, next to the national borders of Greece with FYR of Macedonia, East of the Evzonoi Customs border pass, at close distance from the port of Thessaloniki.
Each site of the solar project cluster is private and has been carefully selected close to the 400 kV HV grid line connecting Thessaloniki, Greece with Dubrovo in FYR of Macedonia. The intention is to connect all the 22 projects with an exclusive line and drive the energy to the UHV line through the new MV/UHV substation, which will be constructed to hub energy also produced by the projects of Greentop Eiriniko S.A. as well as the project of Greentop Solar Anthofyto 12.2 MW capacity. The location of the S/S has been identified and approved by the HTSO. The relevant application has been issued to HTSO (ADMIE) waiting for approval.
Project Description
A new Ultra- High Voltage 400 kV Substation has been approved by the Hellenic Transmission System Operator (ADMHE) and will be constructed under the UHV international powerline connecting Thessaloniki with Dubrovo, passing at a close distance to the Eiriniko projects. An Environmental License for the UHV SS is also in place and Soil conductivity tests have been performed.
The substation will hub energy produced from the Eiriniko wind & solar projects and the Anthofyto project. The construction and operation of this particular substation provides security to the producer for the energy produced. Feeding to the grid will be done without interruptions due to grid limitations or failures. This substation will be of a modular type and will relieve the local Medium Voltage electricity grid by providing access, and hub energy produced from other renewable energy projects in the area, currently halted due to local grids limitations.
Projects Cluster Overview
The above neighboring Projects are developed in the Prefecture of Kilkis, Municipality of Paionia, next to the national borders of Greece with FYR of Macedonia, East of the Evzonoi Customs border pass, at close distance from the port of Thessaloniki. They all hold a Production License, an Environmental License and share the same grid connection point, an UHV S/S 400kV under the existing UHV line.
This project will contribute substantially towards Greece meeting EU targets in cutting down greenhouse emissions, 360K t of CO2 and 4,750t of SO2 per year, & increase its renewables share until year 2020 and 2030.
The implementation of this large-scale project will provide multiple benefits to a region in Greece where unemployment is >40% with locals emigrating to other cities and abroad looking for job opportunities. Businesses are closing or moving to FYROM and Bulgaria.
During construction & operation, the project will give a boost to local economy by providing jobs to local labour and skilled professionals, as well as income to local businesses. Municipality & locals will benefit from a levy of 2.7% of the wind project’s gross income

