An SPV owned 100% by Greentop Energy Systems S.A. founded in Athens, on 17/02/2011. Its sole purpose is to develop, construct and operate a wind project in Central Greece, with a total capacity of 23,1 MW.
Projects
Project Description
The SPV develops a project in the Prefecture of Evrytania, Municipality of Karpenissi, next to the villages of Vraha and Fournas, at the location called Gavraina. The wind park is sited at a height of 1,400 m, on a mountain ridge between the mountains of Tymfristos and Agrafa. The prevailing wind is SSW.
The SPV has been granted with a Generation (Production) License and Preliminary Grid Connection Terms and Conditions have been defined by the Hellenic Transmission System Operator (HTSO/ ADMHE). The project has applied for an Environmental license.
The site does not have any environmental limitations or restrictions and does not fall under any provision of ‘Nature 2000’.
To access the site for the transfer of major equipment, few interventions will have to be made along the road network, from the port to the site.
The wind park will be connected, through a new MV substation to the 150 kV HV power transfer line connecting the city of Lamia with the town of Karpenissi. This substation will also hub energy produced by the projects of Spanos Wind Park S.A. (36,3 MW), Greentop Kokkala Wind Park S.A. (24 MW) and Tria Synora Anaptyxiaki S.A. (30.8 MW). These wind parks are in close distance to one another and all directly are owned by Greentop Energy Systems S.A.